10 exam-style questions with answers and explanations, straight from our 1,030-question bank. Tap an answer to check yourself. When you're ready, take the scored version in the free practice test.
These 10 free EVP questions are organized by exam domain, so you can see how each part of the Earned Value Professional (EVP) blueprint is tested. Reveal the answer and explanation under each question.
Domain 1: Organizing 12% of exam
Question 1
Engineering and manufacturing managers supply staff to a control account under agreed resource commitments. Its control account manager (CAM) has delegated authority for integrated cost, schedule, and technical performance. The functional managers want joint accountability because they supervise the staff. How should the responsibility assignment matrix represent this arrangement?
Show answer & explanation
Correct answer: D - Retain the CAM's accountability and show the functional managers' supporting responsibilities.
Domain 2: Perform Planning and Scheduling Duties 13% of exam
Question 2
Mechanical preparation takes 18 working days and controls verification takes 16. These branches start together; a four-day acceptance test follows only after both finish. Management wants to cut four days from the project's completion. A fully resourced proposal reduces mechanical preparation to 14 days. Using a common working-day calendar with no other constraints or changes, what does that proposal accomplish?
Show answer & explanation
Correct answer: B - A two-day gain; controls verification becomes the branch that determines when acceptance testing starts.
Domain 3: Perform Budgeting Duties 13% of exam
Question 3
A $240,000 work package assigns 30% of its budget to approved design, 40% to fabrication, and 30% to qualification. Fabrication earns proportionally as 20 equal-budget assemblies are accepted. Qualification earns only when all 10 required tests pass. At the status date, design is approved, 12 assemblies are accepted, and four qualification tests have run but none has passed. How much earned value is supported?
Show answer & explanation
Correct answer: A - $129,600
Question 4
A prime contractor's pricing estimate includes its own profit and a negotiated fixed-price subcontract for testing. The supplier's price includes profit, but the prime purchases the defined testing scope for that full price. A reviewer proposes removing profit from both amounts when establishing the prime's performance measurement baseline. Which treatment is correct?
Show answer & explanation
Correct answer: C - Exclude the prime's profit; retain the full purchased subcontract price.
Domain 4: Account Considerations 11% of exam
Question 5
A prime measures a fixed-price instrument subcontract through separately budgeted, accepted fabrication milestones. One milestone is accepted before cutoff. Under the subcontract and approved accounting policy, Finance verifies an incurred liability at the agreed milestone price. No ledger entry or accrual records it; supported estimated actuals are permitted. The supplier's invoice also requests an advance for future installation. For this cutoff, the prime should:
Show answer & explanation
Correct answer: B - Credit the milestone budget and record an estimated actual for the prime's verified liability, treating the installation advance separately.
Domain 5: Analysis and Management Reports 35% of exam
Question 6
Early procurement of high-value equipment has lifted a project's cumulative schedule performance index to 1.07; its cost performance index is 1.03. The data reconcile, but the validated schedule forecasts a finish six weeks late because permit-dependent civil work controls completion. The early equipment delivery does not shorten that path. Which statement belongs in the status summary?
Show answer & explanation
Correct answer: C - Aggregate indices are favorable, while the critical-path finish remains six weeks late.
Question 7
An aircraft-retrofit program has a cumulative CPI of 0.84. Its proposed EAC requires a TCPI of 1.02. First-article engineering is complete. Three representative production batches achieved CPI 1.06 with the crews and rates planned for the remaining repeat work. The detailed remaining estimate includes installation, acceptance testing, and identified risks. On this evidence, how should the proposed EAC be treated?
Show answer & explanation
Correct answer: A - Use the supported estimate and monitor whether production continues to match its assumptions.
Question 8
Fabrication reports a $72,000 unfavorable labor cost variance: $61,000 from excess hours and $11,000 from rates. Rework is concentrated in assemblies made on one alignment fixture. The same qualified operators, using the same material lots, achieve normal first-pass acceptance on a second fixture. Before revising staffing assumptions, which explanation most warrants targeted investigation?
Show answer & explanation
Correct answer: A - An alignment problem with the fixture associated with the rejected assemblies.
Domain 6: Revisions and Data Maintenance 16% of exam
Question 9
A customer engineer requests a new diagnostic feature outside the authorized scope. The engineer may approve technical drawings but cannot authorize contract changes. The feature does not affect existing work, which the project manager remains authorized to continue. Choose the immediate response.
Show answer & explanation
Correct answer: D - Document and route the request to the contract authority; continue unaffected authorized work.
Question 10
Two authorized budget transactions are ready to post: undistributed budget already included in the performance measurement baseline is assigned to control accounts, and management reserve is allocated to future in-scope work. There is no change in contract scope or the contract budget base. Which description correctly reconciles the transactions?
Show answer & explanation
Correct answer: C - Only the reserve allocation increases the performance measurement baseline; the contract budget base stays unchanged.